What happens if the Scrum Team cannot complete its work by the end of the Sprint? (Choose the best answer)
What happens if the Scrum Team cannot complete its work by the end of the Sprint? (Choose the best answer)
A . The Sprints extended temporarily. Lessons are taken to ensure it does not happen again
B . The Sprint is extended and future Sprints use this new duration.
C . The Sprint length is unchanged and the Scrum Team continuously leans and adapts.
Answer: C