An opportunity record, created with a close date of July 30, meets the criteria of a time-dependent workflow rule. The time-dependent action is scheduled for July 23.
What happens if the opportunity is edited before July 23 and no longer meets the criteria?
A . The time-dependent action is automatically removed from the queue.
B . The time-dependent action will execute on July 30.
C . The time-dependent action is put on hold.
D . The time-dependent action will execute on July 23.
Answer: A