What final action should the project manager take before moving to the new project?

A project manager delivered the final project report and is ready to close the project. The company is anxious to start an important project and asks the project manager to start the new assignment immediately

What final action should the project manager take before moving to the new project?
A . Obtain final approval of project deliverables and confirm whether changes were implemented.
B . Confirm whether project documentation has been filed according to company standards
C . Compile the lessons learned during all project stages and hold a meeting to review them.
D . Ensure that procurements have been reviewed and that contracts have been closed

Answer: C