What estimating technique should the contractors use?

After approval of a project scope statement, requests for proposal (RFP) are sent to potential contractors. The project manager indicates that detailed quotes will be required.

What estimating technique should the contractors use?
A . Top-down
B . Bottom-up
C . Analogous
D . Parametric

Answer: B