What else does the project manager need to do before determining the budget baseline?
A project manager is working on the budget for a long-term project. The project manager creates a work breakdown structure (WBS) and estimates the cost for each work package based on past projects.
What else does the project manager need to do before determining the budget baseline?
A . Look at a previous project to ensure the budget totals match.
B . Require all stakeholders to review and approve the estimates.
C . Revise the project timeline and scope based on the WB
E . Add contingency into the budget for inflation and other changes.
Answer: D