What efficiency must be maintained to achieve the current estimate at completion (EAQ?
A project’s budget at completion (BAG) is USS10000. its earned value (EV) is US$2000. and its actual cost (AC) is US$10,000. The planned value (PV) is USS20.000.
What efficiency must be maintained to achieve the current estimate at completion (EAQ?
A . Behind schedule and under budget
B . Ahead of schedule and over budget
C . On schedule and maintaining budget
D . Behind schedule and maintaining budget
Answer: C
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments