What efficiency must be maintained to achieve the current estimate at completion (EAQ?

A project’s budget at completion (BAG) is USS10000. its earned value (EV) is US$2000. and its actual cost (AC) is US$10,000. The planned value (PV) is USS20.000.

What efficiency must be maintained to achieve the current estimate at completion (EAQ?
A . Behind schedule and under budget
B . Ahead of schedule and over budget
C . On schedule and maintaining budget
D . Behind schedule and maintaining budget

Answer: C