What does that project manager need to do to make the team work in a collaborative way?

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?
A . Request the project management office (PMO) for a team of mentors.
B . Allocate time to mentor the team.
C . Update the issue log.
D . Identify any training gaps

Answer: B