What does a burn-down chart measure in a project?
A . Work remaining across time.
B. Business value delivered by the team.
C. Budget remaining across time.
Answer: A
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund