What does a burn-down chart measure in a project?

What does a burn-down chart measure in a project?
A . Work remaining across time.
B. Business value delivered by the team.
C. Budget remaining across time.

Answer: A

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments