What documentation should be created in order to complete the project?

A project manager and project learn have successfully implemented a new product line at their company and are in the process of closing it out. The project manager has obtained acceptance from the internal customer, conducted reviews, and documented lessons learned

What documentation should be created in order to complete the project?
A . Project management plan updates and final product
B . Scope baseline and final product
C . Final product and organizational process assets updates
D . Cost performance baseline and final product

Answer: C