What document should the project manager review?

An organization initiates a large project in a developing country. The project manager, who is also the local stakeholder is very supportive of this project During project execution the project manager is transferred to another country. The new project manager is less supportive of the project because it uses many local resources who could be focusing on other daily responsibilities

What document should the project manager review?
A . Project management plan
B . Organizational process assets
C . Stakeholder engagement assessment matrix
D . Stakeholder engagement plan

Answer: C