What document or resource is likely to be MOST valuable in determining the schedule’s work activity durations?
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company’s board of directors for its consideration.
What document or resource is likely to be MOST valuable in determining the schedule’s work activity durations?
A . Industry publications.
B . Critical path schedules prepared by you for similar completed projects.
C . The Petrochemical Industry New Plant Task Duration Handbook.
D . The cost estimate for the plant prepared by your firm’s estimating department.
Answer: B