A matrixed organization has a history of project schedule and cost overruns. A new project manager learns of this history and wants to avoid the trend. The project manager works with the project team to define, validate, and control all required work to complete the project successfully

What document is produced from this activity?
A . Project charter
B . Project management plan
C . Scope management plan
D . Project scope statement

Answer: D