You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling.
What do you recommend for milestone definition?
A . Enter an offset of -18 days to the finish date of the activity
B . Enter February 10 as fixed date
C . Enter 10 days as duration
D . Enter an offset of 10 days to the start date of the activity
Answer: B