What do you need to be aware of when using multiple pairs of key figures in one copy operator?
Note: There are 2 correct answers to this question.
A . Copying multiple key figures can be processed sequentially
B . Copying multiple key figures on different planning levels is not possible.
C . Necessary source key figures values are disaggregated.
D . Necessary target key figures value are disaggregated
Answer: A, D