What do you have to define in the optimizer settings?
You want to configure transportation proposals in such a way that carrier selection is NOT executed as part of the process and the result of the process is saved in the stages of the freight unit.
What do you have to define in the optimizer settings? Note: There are 2 correct answers to this question.
A . Save route and freight documents
B . Planning strategy: VSR_DEF
C . Save route only
D . Planning strategy: VSR_1STEP
Answer: B,D