What determines whether the planned independent requirements in demand management are consumed by other requirements? Note: There are 2 correct answers to this question.
A . Order type
B . Planning strategy
C . Requirements profile
D . Requirements type
Answer: B, D
Explanation:
The consumption of planned independent requirements by other requirements, such as sales orders or stock transport orders, depends on the planning strategy and the requirements type of the materials involved. The planning strategy defines the basic procedure for planning a material and determines whether the consumption is relevant for planning. The requirements type controls the consumption parameters, such as the consumption mode (forward, backward, or bidirectional), the consumption interval (period of time in which the consumption can take place), and the consumption indicator (whether the consumption reduces the planned independent requirements or not).
Reference: Consumption of Planned Independent Requirements | SAP Help Portal, Planning Strategy | SAP Help Portal, Requirements Type | SAP Help Portal.
Latest C_TS422_2023 Dumps Valid Version with 80 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund