Site icon Exam4Training

What determines the sequence in which materials are planned during the material requirements planning (MRP) run?

What determines the sequence in which materials are planned during the material requirements planning (MRP) run?
A . The control parameters of the MRP run
B. The creation date of the materials
C. The low-level code of the materials
D. The replenishment lead time of the materials

Answer: C

Exit mobile version