Exam4Training

What date and time frame should you use?

You are analyzing the performance data to avoid oversizing of a CI solution.

What date and time frame should you use?
A . Average production time over multiple days
B . Peak production times over multiple days
C . Average production time over a single day
D . Peak production times over a single day

Answer: D

Latest DES-2T13 Dumps Valid Version with 70 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version