You plan to schedule a Live Optics sampling with your customer to size a Dell EMC SC Series array. However, the customer wants to postpone the run until the end of the quarter because there could be more activity on the current storage system.
What course of action is recommended?
A . Wait until the end of the quarter and collect a week-long sampling
B . Take a single-day sampling on any given day because that is sufficient in most instances
C . Wait until the end of the quarter and collect a single-day sampling
D . Take a week-long sampling on any given week because that is sufficient in most instances
Answer: B
Latest DES-1D12 Dumps Valid Version with 60 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund