You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created.
What could be the reason? Note: there are 2 correct answers for this question.
A . The procurement type in the material master is set to in-house Production.
B . The item category of the materials is set tstock item.
C . The material have no material number.
D . The item category of the materials is set tnon-stock item.
Answer: A,B