What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
A . Configuration Management System
B . Project Management Information System
C . Scope Verification
D . Integrated Change Control

Answer: A

Latest CAP Dumps Valid Version with 395 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments