What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?
A . Configuration Management System
B . Project Management Information System
C . Scope Verification
D . Integrated Change Control
Answer: A