You are currently working on creating the activity list for an initiative in your organization.
What characteristic must be assigned to each task in your task list?
A . Procurement needs
B . Risk level
C . Unique number
D . Roles and responsibilities
Answer: C
Explanation:
Each task in the task list should have a unique number to identify the specific task and it should have a description of what the task is.
Answer. B is incorrect. The risk level is not associated with the task list.
Answer. D is incorrect. Roles and responsibilities are not included directly in the task list.
Answer. A is incorrect. Procurement needs are not included in the task list.