What can you check using budget availability control?
You want to set up budget availability control for your projects and internal ordders .
What can you check using budget availability control? 2 Answers
A . The availability of funds in object currency
B . The availability of funds using overall plan value
C . The availability of funds on period level
D . The availability of funds according to tolerance limits
Answer: A,D