A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference .
What can the project manager do?
to improve interactions between the team members in both countries?
A . Ensure full participation of both the product owner and business SMEs in scope planning sessions.
B . Identify virtual communication methods and arrange for regular team meetings accordingly.
C . Explore the opportunity to have both teams colocated.
D . Plan for frequent face-to-face meetings.
Answer: B