What can be an indication that the Product Owner is not spending enough time with the Scrum Team? (Choose the best answer)
A . He is not with the Scrum Team full time.
B . The velocity is dropping.
C . He is surprised by what was delivered in the Increment at the Sprint Review.
D . The burn down chart is not being kept up to date.
Answer: C