What artifact should the project manager share with the stakeholder?

The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue .

What artifact should the project manager share with the stakeholder?
A . Issue log
B. Project management plan
C. Risk management plan
D. Risk register

Answer: D