Managing Strategic Change is an integral part of any portfolio in order to remain aligned with the strategic objectives. Your portfolio has undergone a major strategic change and you are currently determining the volume of work required to do in order to re-align the portfolio .

What are you currently using?
A . Change Analysis
B . Gap Analysis
C . Readiness Assessment
D . Stakeholder Analysis

Answer: B