You need to configure models for the project.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
A . Overlay the existing FinanceExt model and populate the solution definition.
B . Modify the DefaultModelForNewProject setting in the DefaultConfig.xml file and name the model FinanceExt.
C . Create a new model that extends the existing FinanceExt model.
D . Extend the existing FinanceExt model and populate the project model definition.

Answer: A, D

Explanation:

https://www.google.com/amp/s/robscode.onl/d365-set-default-model-for-new-projects/amp/