Exam4Training

What are two possible ways to achieve the goal?

You need to configure models for the project.

What are two possible ways to achieve the goal? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
A . Overlay the existing FinanceExt model and populate the solution definition.
B. Modify the DefaultModelForNewProject setting in the DefaultConfig.xml file and name the model FinanceExt.
C. Create a new model that extends the existing FinanceExt model.
D. Extend the existing FinanceExt model and populate the project model definition.

Answer: B,D

Explanation:

https://www.google.com/amp/s/robscode.onl/d365-set-default-model-for-new-projects/amp/

Latest MB-500 Dumps Valid Version with 117 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version