What are two outputs of Iteration Planning? (Choose two.)
A . Program Backlog
B. Iteration goals
C. Iteration backlog
D. PI Objectives
E. Team Backlog
Answer: B,C
Explanation:
The output of iteration planning is: The iteration backlog, consisting of the stories committed to for the iteration, with clearly defined acceptance criteria. A statement of Iteration goals, typically a sentence or two for each one, stating the business objectives of the iteration.