What are two main reasons why the program predictability measure is important? (Choose two.)
A . It allows the business and other stakeholders to plan effectively
B . It identifies under-performing teams
C . It focuses the Agile Release Train on predictable value delivery
D . It demonstrates the need to fix the scope at the beginning of the Program Increment (PI)
E . It indicates whether the Solution is ready to be released
Answer: B,C