Program Increment (PI) Planning is a major event that requires preparation, coordina-tion, and communication.
What are two key areas a Release Train Engineer should focus on to support a successful PI Planning event? (Choose two.)
A . Organizational readiness – Strategic alignment; roles, teams, and train setup
B . Architectural readiness – Defining the Architectural Runway
C . Operational readiness – Facilitating PI events such as scrum of scrums, Iteration Planning, and System emo
D . Facilities readiness – Space and logistics for the event
E . Process readiness – The operational rhythm that enables SAFe governance
Answer: A,D