A develop completed modification to a customized feature that is comprised of two elements:
Apex trigger
Trigger handler Apex class
What are two factors that the developer must take into account to properly deploy the modification to the production environment?
A . Apex classes must have at least 75% code coverage org-wide.
B . At least one line of code must be executed for the Apex trigger.
C . All methods in the test classes must use @isTest.
D . Test methods must be declared with the testMethod keyword.
Answer: A, B