What are two common PI planning anti-patterns?
What are two common PI planning anti-patterns?
A . Too much time spent analyzing each story
B. Too much time spent prioritizing features
C. Team decides which changes need to happen and when
D. Part-time scrum masters do not have time to plan as part of the team
E. Stories are created for the PI planning iterations
Answer: A, D