What are the various activities performed in the planning phase of the Software Assurance Acquisition process? Each correct answer represents a complete solution. Choose all that apply.

What are the various activities performed in the planning phase of the Software Assurance Acquisition process? Each correct answer represents a complete solution. Choose all that apply.
A . Develop software requirements.
B . Implement change control procedures.
C . Develop evaluation criteria and evaluation plan.
D . Create acquisition strategy.

Answer: ACD

Explanation:

The various activities performed in the planning phase of the Software Assurance Acquisition

process are as follows: Determine software product or service requirements. Identify associated risks. Develop software requirements. Create acquisition strategy. Develop evaluation criteria and evaluation plan. Define development and use of SwA due diligence questionnaires.

ANS: B is incorrect. This activity is performed in the monitoring and acceptance phase of the Software Assurance acquisition process.