What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)
A . By ensuring the meetings start and end at the proper time.
B . By removing impediments that hinder the Development Team.
C . By facilitating Development Team decisions.
D . By keeping high value features high in the Product Backlog.

Answer: B,C

Explanation:

The correct answers are B and C, because these are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity. The Scrum Guide states that “the Scrum Master serves the Development Team in several ways, including … removing impediments to the Development Team’s progress; facilitating Scrum events as requested or needed; and coaching the Development Team in self-organization and cross-functionality.” Therefore, by removing impediments and facilitating decisions, the Scrum Master helps the Development Team focus on their work and deliver value.

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
préexam
préexam
10 months ago

et A ?? en veillant au bon déroulement des daily c’est s’assurer que le framework scrum est bien appliqué !!