What are the two best responses?
A Project Manager working with your Scrum Team has raised concerns about progress and money spent.
What are the two best responses? (Choose the best two answers)
A . Have a discussion with the Project Manager; share the current impediments and forecast for the Sprint.
B . Scrum does not have Project Managers so disregard their concerns.
C . Show the Earned Value Analysis (EVA) report.
D . Share the last stakeholder briefing document prepared by the Product Owner.
E . Promote transparency by sharing the Product Backlog and ensuring the Project Manager has access.
Answer: A,E