What are the two best responses?

A Project Manager working with your Scrum Team has raised concerns about progress and money spent.

What are the two best responses? (Choose the best two answers)
A . Have a discussion with the Project Manager; share the current impediments and forecast for the Sprint.
B . Scrum does not have Project Managers so disregard their concerns.
C . Show the Earned Value Analysis (EVA) report.
D . Share the last stakeholder briefing document prepared by the Product Owner.
E . Promote transparency by sharing the Product Backlog and ensuring the Project Manager has access.

Answer: A,E

Latest PSPO-I Dumps Valid Version with 481 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments