What are the requirements of monitoring risk?
What are the requirements of monitoring risk?
Each correct answer represents a part of the solution. Choose three.
A . Information of various stakeholders
B . Preparation of detailed monitoring plan
C . Identifying the risk to be monitored
D . Defining the project’s scope
Answer: BCD
Explanation:
It is important to first understand the risk to be monitored, prepare a detailed plan and define the project’s scope for monitoring risk. In the case of a monitoring project, this step should involve process owners, data owners, system custodians and other process stakeholders.
Incorrect Answers:
A: Data regarding stakeholders of the project is not required in any phase of risk monitoring.
Latest CRISC Dumps Valid Version with 933 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund