Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the
project.
What are the prerequisites? Note: There are 3 correct answers to this question
A . A bill of material with sales views
B. A material master with sales views
C. Assignment between material and standard network
D. Standard network with activities
E. A production order
Answer: B,C,D