What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?
A . The planned order is converted to a production order.
B . The planned order’s component availability is checked.
C . The planned order generates capacity requirements
D . The planned order’s components are copied to the picking list.
Answer: C