What are the consequences of setting a production order to Technically Complete (TECO)? (Choose three)
A . The order is no longer relevant for material requirements planning.
B . Capacity requirements are set to null.
C . Confirmations are no longer possible.
D . Reservations are no longer relevant for material requirements planning.
E . The order and its operations receive the system status Locked (LKD).
Answer: A,B,D