What are metrics NOT used for?

What are metrics NOT used for?
A . To identify the percentage of work done in test environment preparation.
B . To identify the percentage of work done in test case preparation.
C . To apply to the RAD development model.
D . To measure whether dates of test milestones were met.

Answer: C