Exam4Training

What are appropriate responses if the Scrum Team identifies that the workload in the Sprint Backlog has become greater than their capacity during the Sprint Planning? (Choose the best two answers)

What are appropriate responses if the Scrum Team identifies that the workload in the Sprint Backlog has become greater than their capacity during the Sprint Planning? (Choose the best two answers)
A . The Scrum Team members ensure that the Product Owner is aware, starts the Sprint and monitors progress.
B . Start the Sprint and add additional resources to the Scrum Team.
C . Remove, replace, or make changes to selected Product Backlog items in the Sprint Backlog.
D . Budget overtime in order to meet the commitment.
E . Look for another team that has free capacity to take on the extra work.

Answer: A, C

Latest PSPO-III Dumps Valid Version with 65 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version