What approach should be used in this situation?

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible

What approach should be used in this situation?
A . The team facilitator gets support from external team members.
B . The team members bring in a specialist to help them
C . The product owner moves it to the product backlog.
D . The cross-functional team member work together to complete the activity

Answer: B