You are the business analyst for your organization and you’re working with the project manager to complete some business analysis activities. The project manager has the authority to approve the requirements based on the short iterations of business analysis activities.
What approach of business analysis are you using in this scenario?
A . Progressive elaboration
B . Change-driven
C . Plan-driven
D . Iterative
Answer: B
Explanation:
Change-driven approaches to business analysis deal with rapid delivery of the business value. The
business value is delivered in short iterations in return for acceptance of a higher degree of uncertainty
regarding the overall delivery of the solution. The change-driven approaches are preferred while taking an
exploratory approach for incremental improvement of an existing solution.
Answer. D is incorrect. Iterative is not a valid business analysis approach.
Answer. C is incorrect. The plan-driven approach defines business analysis activities. This approach is used to focus on minimizing up-front uncertainty and to ensure that the solution is fully defined before implementation begins in order to maximize control and minimize risk. It is preferred when requirements are effectively defined in advance of implementation.
Answer. A is incorrect. Progressive elaboration describes the project management approach of refining requirements and project scope, not the business analysis approach.