What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?
Robert’s program is slipping on its schedule and management has asked that Robert find a method to compress the duration of the program.
What approach could Robert take that would not dramatically add risks to program if he added labor to the effort-driven activities within the program?
A . Lead time
B . Crashing
C . Lag time
D . Fast tracking
Answer: B