What additional detail should the SE now consider in the Sizing scenario?

An SE and a prospect decide on a specific node configuration. The SE changes the Sizer scenario from Automatic to manual mode to select the exact configuration decided with the prospect.

What additional detail should the SE now consider in the Sizing scenario?
A . Curator Capacity.
B. Block Awareness.
C. N + 1 availability.
D. CVM Memory overhead.

Answer: C

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments