What activities can you perform from the Overview tab or a project when the view is set to full view instead of compact view? Note: there are 2 correct answers to this question.
What activities can you perform from the Overview tab or a project when the view is set to full view instead of compact view? Note: there are 2 correct answers to this question.
A . Create project announcements
B . Audit project history
C . Manage team groups
D . Create a follow-on project
Answer: A, D