What actions do you have to take to solve the problem?

A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets.

What actions do you have to take to solve the problem?
A . Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Answer: B